Sydney Metro - Central Station Advanced Adit

Client

Laing O'Rourke

Year

2019-2020

Location

Sydney, Australia

Tunnelling Solutions were engaged by Laing O’Rourke in the early stages of this iconic project within Sydney’s Central Station. The concept was to construct a materials-handling tunnel eliminating the need for track closures to remove material from the live platforms 16-23.

The delivery scope comprised of the following:

  • 68m long x 6m wide and 5.5m arched tunnel comprising of Canopy Tubes, Lattice Girders, Shotcrete and GRP Anchor Bolts completed under the live rail above.
  • Tunnelling Solutions Road Header (Matilda) working in Sydney Sandstone completed the works in the extremely sensitive live rail area.
  • 4no culverts stubs to provide launch area for 900mm bottom up vertical bores to live platform
  • Design and Fabricate bespoke vertical auger boring machine to bore from adit culvert stubs to the live platform above.
  • 1.5m x 1.5m wide x 4.5m deep hand excavated with timber support reception shafts constructed on live Platforms for the 900mm bored shaft.
  • Massive public working environment with a huge amount of stakeholder engagement to ensure all risks were mitigated and methodology communicated and understood by all parties.